2020

ANGS-04-U-BAL-GE-001 Well Testing & Appraisal WSCC 040 17 BA Decision Notice (2)

View PDF

ANGS-04-U-BAL-RP-001 Well Testing and Appraisal WSCC 040 17 BA Committee Report

View PDF

ANGS-04-U-BAL-RP-002 Condition 7 Discharge Balcombe 20180514 Rev 1 (2)

View PDF

ANGS-04-U-BAL-RP-003 Condition 8 661913 Rev06 15082018

View PDF

ANGS-04-U-BAL-RP-004 Condition 9 Discharge Balcombe 20180514 Rev 1 (1)

View PDF

ANGS-04-U-BAL-RP-005 Condition 10 & 17 Lighting & Bat 17082018

View PDF

ANGS-04-U-BAL-RP-006 Condition 11 Discharge Traffic Management Plan 27092018

View PDF

ANGS-04-U-BAL-RP-007 Condition 15 Noise Manangement Plan 20082018

View PDF

ANGS-04-U-BAL-RP-008 Condition 18 Discharge Restoration 25042018

View PDF

ANGS-04-U-BAL-RP-009 Condition 18 Discharge Restoration Plan 18052018

View PDF

ANGS-04-U-BAL-RP-010 Condition 19 Discharge Security 17052018

View PDF

ANGS-04-U-BAL-RP-011 Condition 21 Discharge Community Liason Group 21052018

View PDF

ANGS-04-U-BAL-RP-012 Eclipse Lighting Plan18092018

View PDF

EPR Compliance Assessment Report – Pre-operational condition 5 sign off WEBSITE

View PDF

GGS1700 PO05 Vapour Recovery Plan_V4_Website2

View PDF

Angus Energy is committed to supplying all relevant and non-proprietary data to residents, investors, and other stakeholders regarding operations at Balcombe Oil Site. The company aims to be fully transparent at Balcombe and beyond, and is pleased to present the documentation to interested parties. As such, the company publishes below all planning discharge documents relating to the Autumn 2018 7-day well test that was carried out on the Balcombe 2Z well. Furthermore, copies of the vapour recovery plan and corresponding Compliance Assessment Report are also provided. Names and contact details have been redacted.